How to Write an RFI in Construction (With Template)

By Bildgaard. Published .

A request for information (RFI) is a formal written question sent during construction when the drawings, specifications or other contract documents are unclear, conflict with each other, or leave something out. The contractor usually sends it to the architect or engineer, often through the general contractor if the sender is a subcontractor. The written answer becomes part of the project record.

Why RFIs matter

An RFI puts a question and its answer on paper with a date. A verbal answer on site can be forgotten or disputed. A numbered, logged RFI shows what was asked, when, who answered, and whether the answer changed the scope, cost or schedule. Slow or unanswered RFIs can hold up work and may support a request for more time or money, which is why a clear log helps.

An RFI is not a change order, a submittal, or a way to ask for a design. If the answer changes scope or price, follow your contract's change process separately.

What a good RFI contains

  • Project name and number.
  • RFI number. Sequential, never reused.
  • Date sent and date a response is needed. Based on the schedule.
  • To and from. Who is asking and who should answer.
  • Subject line. Short and specific: "Level 2 slab depression at Stair B: conflict between S-201 and A-105."
  • Reference. Drawing numbers, detail callouts, spec section and paragraph.
  • The question. One issue per RFI. State the conflict or gap in plain words.
  • Proposed solution. What you think should be done and why. This speeds up an answer.
  • Impact. Whether the issue affects cost or schedule, and the date by which work is affected.
  • Attachments. Marked-up drawings, sketches, photos.

RFI template

RFI template
FieldEntry
Project / job number 
RFI number (RFI-###) 
Date submitted 
Response needed by 
From (name, company) 
To (name, company) 
Subject 
Drawing / detail reference 
Spec section / paragraph 
Question 
Contractor's proposed resolution 
Potential cost impact (Yes / No / Unknown) 
Potential schedule impact (Yes / No / Unknown) 
Attachments 
Response (design team) 
Responded by / date 
Status (open / answered / closed) 

Numbering and logging

Number RFIs in sequence for each project, and keep a log with the number, subject, date sent, date due, date answered, who answered, and status. Review the log at each weekly meeting. Sort open items by due date. Link each answer to any resulting drawing revision, change order or follow-up. Subcontractor RFIs usually carry the GC's number when forwarded, and many teams keep both numbers on the log.

Response times

Check your contract for a required response time. If it sets none, agree one with the design team at the start of the project. Set your requested response date based on when the answer is needed on site, and give design reviewers realistic time. An RFI sent the day before the work starts invites a rushed answer.

Common mistakes

  • Vague questions. A request such as "Please clarify the framing" cannot be answered without a follow-up.
  • Several issues in one RFI. A partial answer then holds up the whole thing.
  • No reference. Always cite the drawing or spec section.
  • No proposed solution.
  • Asking what is already answered. Check the documents first.
  • Verbal answers never recorded. Follow up with an email or a new RFI.
  • Not stating the impact. If you think the answer may change cost or time, say so when you send it, and check your contract's notice requirements.
  • Ignoring the log. An RFI without a due date or an owner will sit.

Tips for clearer RFIs

Attach a marked-up sketch whenever possible. Write the subject line so someone scanning a list of 80 RFIs can find it. Send the RFI to the person who can decide, and copy those who need to know. Close the loop: when the answer arrives, confirm that it resolves the issue or send a follow-up.

Frequently asked questions

Who answers an RFI?

Usually the architect or engineer of record, sometimes with input from the owner or a consultant.

Is an RFI the same as a change order?

No. An RFI asks for clarification. A change order modifies the contract. An answer may lead to one.

How many RFIs is too many?

There is no set number. A large count can point to incomplete documents, and each one should still be needed.

Can a subcontractor send an RFI directly to the architect?

Typically not. Contracts usually route them through the general contractor. Check your subcontract.

Try it on your own projects

14-day free trial of the Max plan. No credit card required.

Sources